Cadeler A/S (NYSE:CDLR) reported a 65% increase in third-quarter revenue as its expanded fleet and the acquisition of Menck contributed to sales, though project costs, vessel downtime and acquisition expenses weighed on profitability.
Revenue rose to EUR 255.1 million from EUR 154.3 million a year earlier. Adjusted earnings before interest, taxes, depreciation and amortization (EBITDA) increased to EUR 120.4 million from EUR 109.1 million, while net profit fell to EUR 55 million from EUR 64.6 million.
Chief Financial Officer Peter Brogaard said the decline in net profit reflected Menck transaction costs, higher depreciation and financing costs that are now flowing through the income statement rather than being capitalized as part of the newbuild program.
The offshore wind installation company maintained its full-year outlook for revenue of EUR 910 million to EUR 1 billion and adjusted EBITDA of EUR 435 million to EUR 525 million. It also reported a contract backlog of approximately EUR 2.4 billion.
Vessel downtime adds to costs
Chief Executive Officer Mikkel Gleerup said an incident at the Port of Tyne took the Wind Orca out of operation for a period during the quarter. The vessel has since resumed work, and the company expects to recover the lost time before the project ends next year, he said.
Wind Maker also experienced unplanned downtime and additional costs because of rapid crane wire degradation, which Gleerup described as an industry-wide issue. Cadeler is working with suppliers and equipment manufacturers on solutions and positioning spare parts near vessels to reduce future delays.
During the question-and-answer session, Gleerup said Wind Maker is expected to undergo work on the wire issue in the first quarter of 2027. Wind Mover, Wind Keeper and other vessels with the same type of crane will likely need similar work, he said.
Cadeler has decided to perform maintenance on Wind Peak and does not expect the vessel to work again this year. Wind Zaratan is in transit to Europe and also will not be working, Gleerup said.
Unadjusted fleet utilization was 78%, compared with 92% a year earlier, Brogaard said. Adjusted for planned dry docking and transportation from the shipyard, utilization was 90.9%, compared with 92.2% in the prior-year quarter.
Hornsea 3 progress and contract awards
Cadeler has passed the halfway point on monopile installations at the Hornsea 3 offshore wind project, Gleerup said. Turbine installation has also begun, with Wind Pace starting its first installation cycle after loading six turbines.
Asked whether Hornsea 3 was on budget and schedule, Gleerup said the project was proceeding on an agreed schedule that had changed early in the project for several reasons. He said Cadeler had spent more on transportation, including the use of three transport vessels, and had used some project contingency to accelerate that work.
The company also secured a firm contract for Wind Apex on the Dogger Bank project, beginning in the third quarter of 2027 and running into 2028. Gleerup said the vessel could be used on Dogger Bank C as well as A and B at the customer’s discretion.
Cadeler has also signed an exclusivity agreement for foundation and turbine installation at a large U.K. offshore wind farm from 2030. Gleerup said he expects vessel reservation and preferred supplier agreements to convert into firm contracts as the industry advances through upcoming milestones.
Wind Apex was 87% complete and on track for delivery in the second quarter of 2027, Gleerup said. He added that Wind Ace, delivered ahead of schedule, was in transit to Europe for final mobilization.
Menck integration and financial position
Menck, acquired on Aug. 11, contributed EUR 24 million in revenue and EUR 14 million in costs during the period it was included in the quarter, Brogaard said. Cadeler expensed approximately EUR 7 million in transaction costs related to the acquisition.
Gleerup said it was too early to realize acquisition synergies. Cadeler expects eventually to offer customers combined vessel and hammer packages while continuing to operate Menck at arm’s length so it can serve other industry participants.
Brogaard said Cadeler plans to provide Menck segment reporting in its annual report in March and might introduce historical reporting on a quarterly basis in 2027, although it does not plan to provide specific guidance for Menck.
Cadeler ended the quarter with EUR 140 million in cash and an undrawn EUR 100 million revolving credit facility. Brogaard said the company was in advanced discussions with banks on a refinancing that would combine the Menck acquisition bridge loan with financing on several vessels.
Looking ahead, Gleerup said offshore wind commercial momentum was improving, pointing to upcoming auctions in the U.K., France and South Korea. He said 16 gigawatts of capacity had been awarded globally year to date, above the level seen in 2025.
About Cadeler A/S (NYSE:CDLR)
Cadeler A/S is a Denmark-based offshore wind services company that provides vessel and installation services for offshore wind farms. Its work includes transporting and installing wind turbines and their foundations, supporting the construction and maintenance of offshore wind projects. The company operates specialized offshore vessels designed for the demanding conditions of wind farm installation. Cadeler serves project developers and other customers across international markets, including Europe and other regions with offshore wind activity.